|
Can
number of contingencies be more than one?
|
|
Yes.
In each contingency user defined no. of elements can be outaged.
|
|
Whether
Transformer primary should always be H.V.?
|
|
Primary
voltage can be either H.V. or L.V. depending on the taps provided.
|
|
Why
Cost Coefficients are given in Generator data?
|
|
These
are the cost coefficients used in real power optimization study.
|
|
Why
breaker rating is given in all menus?
|
|
The
breaker rating in all menus is just to verify whether the fault MVA
is above or below the breaker rating.
|
|
Where
participation factor field is used?
|
|
Participation
factor is considered in Flat Frequency Control option to simulate the
secondary control effect.
|
|
Difference
between Schedule power and real power.
|
|
Schedule
power is the power generated by the generator at that instance and it
should be less than or equal to maximum real power generation.
|
|
What
is the significance of Contingency Weightage?
|
|
Contingency
Weightage is used to increase the severity of given outage for a particular
bus or line. Normally the weightage value is unity. However, if a particular
bus voltage deviations should not occur for any outage, and even for
small deviations, that outage need to be given higher ranking, then
the bus weightage no. is given greater than unity say, 5. Then the voltage
deviation is multiplied by 5 times, and hence the contingency ranking
will go high. For 400 kV buses and buses connected to neighbouring grid,
the weightage can generally be increased, then line weightage is given
more than unity. For tie lines and important lines in the grid, which
should never be overloaded, line weightage can be increased.
|
|
Why
primary grounding resistance or reactance is used?
|
|
Primary
grounding resistance or reactance is used to add neutral ground resistance
or reactance to reduce the fault current or to introduce any earthing
transformer. It is in elements data of transformer.
|
| How to convert H value from machine base to system base? |
|
|
|
What
is the significance of Phase shifting transformer / Phase shift angle?
|
|
Phase
shifting transformer is used in certain systems to push more power in
a specific line by introducing angle difference . The phase shift angle
in the element data corresponds to the shift given to boost the power
flow. Phase angle in the library is the phase shift introduced due to
vector connection i.e. 1'O clock position or 11' O clock position etc.
|
|
|
|
|
|
Concepts of tie
line with reference to MiPower.
|
|
The
Tie line refers to those lines connecting one utility to other or those
lines, which island the system, when kept open. In inter connected operation
of power system, it is the responsibility of individual utility to operate
the system such that tie line exchange remains constant, Consider two
systems A& B connected by a tie line as shown in figure.
|
|
|
|
Following
an increase in load in area B, say by 25 Mw, after the primary control
(governor action), a case may arise wherein A will be exporting 10MW
extra to B. Hence the representation becomes.
|
|
|
|
If
the flat tie line control were to be there, then A to B should be brought
back to 50 MW I.e. the tie line scheduled power. In order to do that,
rise signal should be given to generator in area B to increase the generation.
The control is called secondary control or AGC (Automatic generation
control). In MiPower, it is possible to schedule the tie line flow,
by changing the generator set points of all generators trying to participate
in the secondary control.
|
| |
|
A
simple system with two generators and 4 loads all connected at same
voltage through bus couplers. The total load is 4x7.5MW. One generator
is scheduled for 20 MW and other is slack with generation capacity of
10 MW, the program is not saying converged but it shows generation output
of slack generator as 29.54 MW with 0 MVAR and other generator with
0 MW and 12 MVAR while MVAR load total is 13 MVAR. What is the reason
?
|
|
·In
Elements - Generator Data there is one Heading called as "Real power
optimization Data under which Give Real Power Min = 0.0, And Real Power
Maximum = ( your specified power or scheduled power )
|
|
·
If in the system, generation is more and load is less, slack bus takes
/ absorbs additional power.
|
|
·
Observe the following in the LFA report.
|
|
Total
Real Power Generation:
|
|
Total
Reactive Power Generation:
|
|
Total
Real Power Load
|
|
Total
Reactive power Load
|
|
The above values should almost match to get converged result.
|
|
Which
are the primary parameters considered in a load flow study?
|
|
P
Active power into the network.
|
|
Q
Reactive power into the network.
|
|
|V|
Magnitude of bus voltage
|
|
&
Angle of bus voltage referred to a common reference.
|
| |
|
|
 |
|
Which are the
parameters considered for short circuit study?
|
| Generator |
|
·Transient(Xd')
or sub-transient (Xd'') reactance is considered for +ve sequence.
|
|
-ve sequence reactance X2 approximately equal to Xd''
|
|
·Zero
sequence reactance is 0.1 to 0.7 times Xd''
|
|
Transmission
Line
|
|
·+ve
seq impedance Z1 equal to -ve seq impedance Z2
|
|
·
Zero seq impedance Z0 depends upon return path, ground wires and earth
resistivity.
|
|
X0
is 2 to 2.5 times +ve seq reactance X1
|
|
R0
is 5 to 10 times +ve seq reactance R1
|
|
B0
is 0.6 to 0.8 times +ve seq susceptance B1
|
| |
|
Why
Generator MVA rating, transformer MVA rating are not appear in short
circuit report?
|
|
In
the load flow study the transformer, Generator MVA rating are relevant
as the loading on the equipment are compared with the rating.In short
circuit study the fault level should be compared with breaker rating
. Hence only breaker ratings are given in short circuit study.
|
|
In
short circuit study R / X ratio of short circuit path is mentioned.
What does it signify and how is it calculated?
|
R/X
ratio of short circuit path is computed in case of 3 phase fault.
The value is used in the selection of asymmetrical braking capacity
from the symmetrical braking capacity. The asymmetrical braking capacity
should be selected based on the R/X ratio ( i,e resistance to reactance
ratio of driving point impedance and the breaker operating cycles.
Please refer Chapter 10, Section 10.1 & 10.6 of "Elements of Power
System Analysis", Fourth edition, McGraw Hill publication by W.D Stevenson,
for further details.
|
 |
Transient
Stability Study
|
|
A
3phase to ground fault at a particular bus , then the program is giving
"Divide by zero" Error.
|
|
Divide
by zero error which encountered is due to fault impedance value which
might be zero. If you want to neglect the resistance give fault impedance
value as 0.000001.
|
|
When
a frequency of bus is plotted where generator is removed, a steady frequency
of 50 Hz is shown for total duration of study. Why is it so ?
|
|
Once
the generator is removed from the system the program assume that the
user is not interested in its bahaviour, rather he is interested in
rest of the system. Hence generator machine equations are not solved.
|
|
For
Transient Studies MiPower should be capable of simulating fault at any
length of line.
|
|
Simulation
of fault at any length of line in transient stability study is not possible
with the POWERTRS. However, a dummy bus can be created at the required
location and fault can be created at that bus.
|
|
Give
frequency calculation procedure when different generators are swinging
at different frequencies.
|
Frequency
at any bus is computed by the expression
|
 |
|
In
transient stability we can not see the plots at the load buses. Only
at generator buses plots can be seen.
|
|
To
view load bus plots select those buses in VIZS buses. These plots are
stored in the database area under TRS directory. In TRS directory bin
files with M or L with .bin extension will be there . Open graph utility
and press import button and browse the bin file 1AecoL.bin file in the
database area under TRS directory . In this bin file you can see the
line flows and r-x plots and load buses plots.
|
|
On
clicking Graph button from Database Manager, program opens the machine
plots(eg. 1Aeco0M.bin) bin file. So to view load buses plot click New
button and press import button and browse the bin file 1Aeco0L.bin file
in your database area under TRS directory. In this bin file you can
see the line flows and r-x plots and load buses plots (if you open Graph
through Database Manager).
|
 |
| |
|
Relay
Co-Ordination
|
|
How
to give instantaneous setting to overcurrent relays?
|
 |
|
Phase
instantaneous setting factor for R1 (in relay Database for Example 156
(CADG-51 (PI))
|
| Min
= 2.5, Max = 20 |
| Phase
instantaneous setting factor for R1 (In Element Relay) = 1.3 |
| Let the
fault current at Bus-2 if Fault occurs at vicinity of Relay R2 = 400 Amps |
| Then
Relay setting of R1 = 1.3 * 400 = 520 Amps |
| Then,
Setting calculated by the relay starts from minimum setting |
| I.e.,
2.5 * 800 = 2000 > 520 Amps |
| Therefore
Setting of the Relay = 2.5 |
|
If any relay in the library is selected, it should have instantaneous
element and its setting should have been entered in Relay Database
|
|
Under setting select
Instantaneous Phase
|
|
For
example Refer Relay 136CDAG-51P1 stands for Phase Instantaneous)
|
|
Click
on Setting Instantaneous Phase .It has a minimum setting of 2.5.and
maximum setting of 20
|
|
With respect to
the rated current of
|
|
1
Amp meaning that Minimum Setting = 2.5 times rated current.
|
|
Maximum setting
= 20 times rated current
|
|
(Typical values
are Min = 2.5 Max = 20)
|
|
Then
in element typical value of Instantaneous factor will be 1.3 meaning
that it has been set to 130% of remote bus fault current i.e. for this,
relay should not operate instantaneously for remote bus fault current.
|
|
What
is the minimum requirement of data for different power system elements
like Motor, Transformer, Load, Line for carrying out relay co-ordination
studies.
|
| Minimum
data required for relay co-ordination : |
|
For all the elements, the short circuit data is a must i.e.
|
|
a)
for generators, ra,X'd , X''d, X2 and X0 are required along with its
MVA rating.
|
|
b)
for line, positive and zero sequence parameters are required.
|
|
c)
for transformer, MVA rating, impedance value, vector group, neutral
grounding impedance if any are required .
|
|
d)
for Induction motor, it is difficult to get the various parameters.
However, we can make the approximation as r1 is negligible. X1 is negligible.
Xm is very high. Z = sqrt(r2 x r2 + X2 x X2) corresponds to starting
impedance taking 5 to 6 times as starting current. r2 and X2 are separated
knowing the starting power factor which is in the
|
|
range 0.17 to 0.2. Motor thermal characteristics (hot and cold ) is
required to select the motor relay.
|
|
Other data required for the relay co-ordination is CT details, relay
location, type of relay and individual relay characteristics as per
relay manufacturer catalogue.
|
|
How
to set Power Swing blocking relay ?
|
|
Power
swing blocking : From power system operation point of view it is not
desirable to obtain tripping from a distance relay during a power swing.
The fluctuations of voltage and current occuring in such a case can
make it impossible for the relay to discriminate between a 3 phase fault
and a heavy power swing. Detection of power swing is made by measuring
the time that elapses between the operation of the two concentric impedance
elements. The output from the impedance elements is fed to a logic circuit
where it is determined whether it is a power swing or a fault that has
occured on the network. This is done by considering the fact that the
change in apparent impedance during power swing is very slow compared
to the sudden change when a fault occurs. The time interval used in
the power swing blocking element is 35-40 ms which means that if a change
in apparent impedance is larger than this fixed time the power swing
blocking element will block the operation of the distance relay for
approximate 2 seconds. On the other hand if the change is faster than
35-40 ms then distance relay is permitted to operate in the normal way.The
power swing blocking setting can be set if the distance relay is provided
with power swing blocking element. For ex.for the RAZFE relay panel
constant k4 gives the setting for power swing blocking element.
|
|
How
to select Earth fault relay plug setting ?
|
|
The
zero sequence fault current through the protective devices is determined
by the fault study. 10% unbalance is assumed ( it can be user defined
also) i.e. the relay should not operate for a fault current ( 0.1 x
ilmax ) flowing through it.
|
|
For
a given secondary rating different pickup currents are available for
earth fault setting.
|
| Following
conditions are checked : |
| Percentage
setting x CT primary rating > Unbalance factor x ilmax. |
| If this
condition is satisfied, |
|
The
ratio of primary zero sequence maximum fault current is checked. This
should be less than the percentage setting x CT primary rating and Maximum
overload capacity.
|
 |